5 governors call for PJM capacity market rule changes to reduce ‘unnecessary’ consumer costs

Talen Energy’s 966-MW, coal-, gas- and oil-fired Herbert A. Wagner power plant near Baltimore. Governors from Delaware, Illinois,

Five governors are urging the PJM Interconnection to reform its capacity market rules and interconnection queue process to prevent “unnecessary” costs for electricity customers.

PJM’s last capacity auction in July will cost consumers a “staggering” $14.7 billion, which could hurt economic development, according to a letter from the governors of Delaware, Illinois, Maryland, New Jersey and Pennsylvania sent Friday to PJM.

“We remain concerned that the current years-long PJM interconnection process severely limits the ability of high capacity prices to encourage the development of additional capacity,” the governors said. “If developers cannot expect to get through the interconnection queue before a reasonably near-term delivery year, then additional energy projects cannot be deployed in time – no matter how high prices rise.”

The governors said they support PJM’s plan to delay the upcoming auction by about six months so it can work with stakeholders to make changes to its market rules.

The Organization of PJM States, Inc., the PJM’s independent market monitor and the PJM Power Providers Group, or P3 Group, which represents generators, support various market reforms. The Sierra Club and other environmental groups filed a complaint arguing that PJM’s rules for reliability must-run units unfairly increases capacity prices and should be changed. Separately, the governors on Friday told the Federal Energy Regulatory Commission they support the complaint and PJM’s plan to delay a capacity auction that is set to be held in early December.

The governors asked PJM to include RMR units in upcoming capacity auctions, noting that OPSI, the market monitor and the groups behind the complainant say that making the change would save consumers between $3 billion and $5 billion in the next auction without undermining market competitiveness or necessary price signals.

 

Para leer más ingrese a:

https://www.utilitydive.com/news/governors-pjm-capacity-market-auction-opsi-p3-ls-pow
¡Haz clic para puntuar esta entrada!
(Votos: 0 Promedio: 0)

Compartir artículo

Deja un comentario

Tu dirección de correo electrónico no será publicada. Los campos obligatorios están marcados con *

Busca los documentos, noticias y tendencias más relevantes del sector eléctrico

Buscador de documentos
Buscador de noticias y tendencias

Banco de Información

Descripción del semáforo tecnológico

Los documentos se clasifican en varios colores tipo semáforo tecnológico que indican el nivel de implementación de la tecnología en el país

Tecnología en investigación que no ha sido estudiado o reglamentado por entidades del sector.

La tecnología se aplica de manera focal y se encuentra en estudio por parte de las entidades del sector.

La tecnología se aplica de manera escalable y se encuentran políticas y regulaciones focales establecidas.

La tecnología se aplica a través de servicios  y se encuentran políticas y regulaciones transversales establecidas.

La tecnología se aplica de manera generalizada  y se tiene un despliegue masivo de esta.

Para acceder a todos los documentos publicados y descargarlos ingresa aquí