Before one of the largest baking companies in the world installed a solar microgrid with a 30-ton battery at its food processing plant in San Jose, Costa Rica, the plant experienced two to five power interruptions daily, either in the form of outages or poor power quality.
When such power snags occurred at the plant, conveyor belts moving baked goods to and from ovens stopped, and the baked goods burned. These power interruptions can cost $2,000 to $15,000 per event, said Ignacio Salazar, head of special projects for Greenenergy, a San Jose-based solar microgrid provider that deployed the Bimbo system in January.
Working with Greenenergy, the bakery installed solar PV with a total peak capacity of 162 KW at three sales centers, a distribution center and on the roof of the processing plant. At the plant, the company also added the battery, which has 2.7 MWh of capacity.
The PV installations are located within a 50-kilometer radius of each other, Salazar said. Each PV installation serves its own building and only the PV at the food processing plant is part of the microgrid.