The Federal Energy Regulatory Commission should only grant incentives for building power lines after they have been approved by state utility regulators, according to FERC Commissioner Mark Christie.
Christie had previously called for eliminating incentives such as “construction work in progress,” which allows a utility to recover its expenses while it is building a project instead of waiting for a rate case after it is placed into service.
“This compromise would ensure that transmission incentives ultimately are awarded to projects that are worthwhile from the state-focused, consumer-oriented perspective and that the resulting rates are just and reasonable under the [Federal Power Act],” Christie said Thursday in a dissent to a FERC order approving incentives for PSEG Renewable Transmission.
Christie has long argued that FERC’s policy of providing financial incentives for transmission projects shifts risks and costs onto ratepayers.
The latest case centers on a 70-mile, 500-kV transmission line PSEG, owned by Public Service Enterprise Group, plans to build in Maryland. The $424 million project is part of a group of transmission projects that grew out of the PJM Interconnection’s 2022 Regional Transmission Expansion Plan Window 3 competitive solicitation process. The projects are designed to bolster grid reliability.
Para leer más ingrese a:
https://www.utilitydive.com/news/ferc-christie-transmission-incentives-cwip-abandoned-pseg-pjm/