- Despite record temperatures last week and a new peak demand record, the Electric Reliability Council of Texas said it was able to maintain service without conservation requests, which it required last summer. Large additions of renewables and battery storage, along with some new gas-fired generation, have made the difference, according to grid officials.
- More gas-fired generation is under development with state support. Developers of more than 38,000 MW of potential new generation have applied for low-interest loans under a state program voters authorized last year.
- Austin Energy said Sunday that the utility has completed a “permanent fix” at a substation in the southwest part of the city that failed Thursday night, briefly leaving 6,400 customers without power as a heat wave blanketed the area. The transformer failure was not the result of excessive heat or demand, the utility said.