National Grid USA and Constellation Energy floated proposals for prioritizing interconnection requests to get generation and energy storage online faster during a panel discussion at a Federal Energy Regulatory Commission workshop on Tuesday.
FERC last year issued its Order 2023, which included a requirement that transmission providers adopt a first-ready, first-served cluster study process to weed out speculative projects in interconnection queues. The agency’s two-day workshop is exploring potential options for further improvements to the grid interconnection process.
The grid interconnection backlog in the United States grew 30% last year to 2.6 TW, according to Lawrence Berkeley National Laboratory. As generating and energy storage projects wait for interconnection studies to be completed, the North American Electric Reliability Corp. has been warning about potential power supply shortfalls in many parts of the continent.
“With reliability as the overriding goal of interconnection, that means prioritizing those generation resources that can be built quickly and efficiently, and that give us the most generation capacity as quickly as possible at the least burden to customers,” FERC Commissioner Mark Christie said Wednesday.