Efforts to expand and modernise electricity transmission grids around the world face mounting challenges as supply chain bottlenecks intensify, according to a new IEA report. Prices and procurement times for essential components like power transformers and cables have almost doubled in four years, creating significant hurdles for grid developers.
The report, Building the Future Transmission Grid: Strategies to Navigate Supply Chain Challenges, highlights that developing transmission infrastructure is essential for energy security and reliable electricity delivery. The supply chain challenges facing the sector come as the world moves toward the Age of Electricity, with global power consumption set to increase strongly in the years ahead. This trend results from the growing electrification of industrial activity; rising use of air conditioning, appliances, electric vehicles and heat pumps; and the expansion of data centres to support the rapid development of artificial intelligence.
While permitting remains the primary cause of delays in transmission projects, particularly in advanced economies, supply chain issues have emerged as a critical limitation. An IEA survey of industry leaders found that procurement now takes two to three years for cables and up to four years for large power transformers – twice as long as in 2021. Specialised components face even longer delays, with lead times for direct current cables – often used for long-distance transmission – extending beyond five years. The price increases for components are equally concerning. In real terms, cable costs have nearly doubled since 2019 while power transformer prices have increased by around 75%.
Para leer más ingrese a: