The PJM Interconnection on Tuesday floated a plan to allow a limited number of generating projects that could address reliability needs to jump into an interconnection study cycle early next year.
The “reliability resource initiative” is a response to unprecedented demand growth forecasts coupled with a slow pace of bringing new power plants online and looming generator retirements, according to Donnie Bielak, PJM’s director for interconnection planning.
“We need to do something, and do something now,” Bielak said Tuesday during a PJM Planning Committee meeting.
The proposal comes as PJM is clearing out a backlog of interconnection requests that had been put on hold and are being reviewed under a three-track transition process to a fully reformed interconnection study framework. PJM plans to begin studying new interconnection requests by mid-2026 under its reformed process.
PJM is finishing generator interconnection agreements for its roughly 24.5-GW “fast track” interconnection review and is in the second-phase of its 26.2-GW Transition Cycle 1 process, according to Bielak. A window for eligible projects to enter the roughly 96.2-GW Transition Cycle 2 process closes on Dec. 17.
Projects in the three tracks are heavily tilted toward solar energy, Bielak noted. “If you look at that from an operational standpoint, you’re kind of putting all your eggs in one basket, and what we’re looking to do is really try to diversify … kind of hedge our position in being able to get as much generation online as quickly as possible to meet the reliability demands that we have coming up,” he said.