PJM aims to fast-track reliability projects in interconnection queue

The Guernsey power station, a 1,875-MW, gas-fired power plant near Byesville, Ohio, owned by Apex Power Group and Caithness Energy.

The PJM Interconnection on Tuesday floated a plan to allow a limited number of generating projects that could address reliability needs to jump into an interconnection study cycle early next year.

 

The “reliability resource initiative” is a response to unprecedented demand growth forecasts coupled with a slow pace of bringing new power plants online and looming generator retirements, according to Donnie Bielak, PJM’s director for interconnection planning.

 

“We need to do something, and do something now,” Bielak said Tuesday during a PJM Planning Committee meeting.

 

The proposal comes as PJM is clearing out a backlog of interconnection requests that had been put on hold and are being reviewed under a three-track transition process to a fully reformed interconnection study framework. PJM plans to begin studying new interconnection requests by mid-2026 under its reformed process.

PJM is finishing generator interconnection agreements for its roughly 24.5-GW “fast track” interconnection review and is in the second-phase of its 26.2-GW Transition Cycle 1 process, according to Bielak. A window for eligible projects to enter the roughly 96.2-GW Transition Cycle 2 process closes on Dec. 17.

 

Projects in the three tracks are heavily tilted toward solar energy, Bielak noted. “If you look at that from an operational standpoint, you’re kind of putting all your eggs in one basket, and what we’re looking to do is really try to diversify … kind of hedge our position in being able to get as much generation online as quickly as possible to meet the reliability demands that we have coming up,” he said.

 

Para leer más ingrese a:

https://www.utilitydive.com/news/pjm-fast-track-reliability-projects-interconnection-queue-invenergy/729311/

¡Haz clic para puntuar esta entrada!
(Votos: 0 Promedio: 0)

Compartir artículo

Deja una respuesta

Tu dirección de correo electrónico no será publicada. Los campos obligatorios están marcados con *

Busca los documentos, noticias y tendencias más relevantes del sector eléctrico

Buscador de documentos
Buscador de noticias y tendencias

Banco de Información

Descripción del semáforo tecnológico

Los documentos se clasifican en varios colores tipo semáforo tecnológico que indican el nivel de implementación de la tecnología en el país

Tecnología en investigación que no ha sido estudiado o reglamentado por entidades del sector.

La tecnología se aplica de manera focal y se encuentra en estudio por parte de las entidades del sector.

La tecnología se aplica de manera escalable y se encuentran políticas y regulaciones focales establecidas.

La tecnología se aplica a través de servicios  y se encuentran políticas y regulaciones transversales establecidas.

La tecnología se aplica de manera generalizada  y se tiene un despliegue masivo de esta.

Para acceder a todos los documentos publicados y descargarlos ingresa aquí